SRINAGAR, AUGUST 28: According to the Chief Engineer, Distribution, KPDCL, in order to carry out the works regarding raising height of 11 KV feeders under the 33 KV main bus conductor by way of erection of one no. 11 mtr long ST Pole and shifting of 33 KV Wanganpora-Takanwari-BAMK line from deteriorated composite wooden pole to 11 mtr long ST Pole at Narwara, shutdown of 33KV Wanganpora Takenwari-BAMK line shall be observed due to which 33/11KV Receiving Station at Takenwari shall remain off while power supply to Shanglipora, Sangam and adjoining areas will be affected from 08:00 AM to 12:00 Noon on 31 August, 2025.
Also in this connection, shutdown of 33 KV Wanganpora-Khanyar Rainawari line shall be observed due to which 33/11KV Receiving Stations at Khanyar & Rainawari shall remain off while power supply to Miskeen Bagh, Rozabal, Maqdoom Sb, Radhpora, Hazari Bagh, Nowhatta, partially jogilankar, Kondabal, Hassanabad and adjoining areas will be affected from 08:00 AM to 10:00 AM on 31 August, 2025.
Moreover, the shutdown of 33 KV GIS (Nowshera) BAMK line shall be observed due to which 33/11KV Receiving Station at BAMK shall remain off while power supply to Industries, Raja Colony, Zadibal, Bota Kadal, Gili Kadal, BSNL Exchange and adjoining areas will be affected from 10:00 AM to 12:00 Noon on 31 August, 2025.
Similarly, in order to carry out the 11 KV Reconductoring, LT AB Cabling and branch cutting, shutdown of 33KV Badampora-Kurhama Dab line shall be observed due to which 33/11KV Receiving Stations at Kurhama, Dab, GCET, Sainik School shall remain off while power supply to Kurhama, Youngpora, Baroosa, Old Dab, Checki Baba, Sainik School, Rabitar, Kondbal, GCET, Safapora and adjoining areas will be affected from 09:00 AM to 03:00 PM on 31 August, 2025.